This week we constructed and raised our first outer wall (11/30 - 12/4).
Monday: We painted on a waterproof coating for our 3/4 in. tongue and groove plywood to keep the decking from soaking up the "Juneau Sunshine."
Tuesday: We moved the waterproofed plywood and some other lumber to the job-site.
Wednesday: We pre-fabricated all the pieces of the wall. Work was rough and miserable due to weather.
Friday: We put up scaffolding in preparation to raise the right wall!