Week 2/8 - 2/12
Monday: Day off
Tuesday: finished the last of the Tyvek wrap around the house.
Wednesday: Dug a hole for the subterranean pipe-network in the garage.
Friday: Today we unloaded a delivery of shingles, windows, and pink-board. We also had several new people start working with us from SAGA
Week 2/1 - 2/5
Monday: Today we had a framing inspector come and inspect the house so far, we passed the inspection and can now move on to wrapping the house.
Tuesday: Started to wrap t he house in Tyvek which will help keep out moisture.
Wednesday: Continued to add Tyvek to the house.
Friday: Today we kept adding the Tyvek, but it became more complicated due to the areas needing to be covered being fairly high off the ground.
Saturday, February 6, 2010
Sunday, January 31, 2010
Interior walls
This week we found ourselves short on man-power since 3 of our workers switched out of the class at semester.
Monday: We worked on finishing of the roof, and adding the last of the sheathing to the outer walls, this involved some very tricky scaffolding work.
Tuesday: Started framing the interior partition walls and continued to finish the last of the exterior sheathing
Wednesday: Continued to frame the partition walls, and put several in place.
Friday: Quickly went through a checklist in order to help the house pass the framing inspection. this included making sure the bottom plates of all the walls were nailed correctly, making sure the sheathing was installed correctly, and double checking the Ice and Water shield.
Monday: We worked on finishing of the roof, and adding the last of the sheathing to the outer walls, this involved some very tricky scaffolding work.
Tuesday: Started framing the interior partition walls and continued to finish the last of the exterior sheathing
Wednesday: Continued to frame the partition walls, and put several in place.
Friday: Quickly went through a checklist in order to help the house pass the framing inspection. this included making sure the bottom plates of all the walls were nailed correctly, making sure the sheathing was installed correctly, and double checking the Ice and Water shield.