Week 5/17 - 5/21
This week we received a shipment of Drywall and insulation, we also started adding in the ventilation.
Monday: We did odd jobs around the house in order to prepare for the drywall.
Tuesday: We received the shipment of drywall and began moving it into position for the Drywall crew.
Wednesday: We continued with Tuesdays work and then we began to install the ventilation on the second floor.
Friday: We kept working on adding ventilation to the house.