Thursday, April 21, 2011
This week, we caulked and sided the north eve side of the home and start placing starter shingles on the main roof. Along with siding, we did some pick-up framing installing the upstairs bathroom sliding door, dug most of the trench for the electrical line, installed the exhaust through the carport for the HRV system, and finished installing all the exterior doors. Next week, its on to the South side of the home then finally onto the main roof pending sunny weather.
First class on exterior door installation
Putting down sealant for back door entrance
Installing bird blocking in between rafter tails
Siding completed this week on the North side of home
Cutting the concrete board
Installation kit for upstairs bathroom sliding door
Diligently digging to bury electrical conduit line
Caulking all the seams around the home
Taking a break from the rain