This week we resumed work on the house again refreshed after spring break. In these five days we successfully framed the interior of the entire first floor, as well as adding in the staircase.
Monday: We started framing the non-load bearing partition walls for the first floor.
Tuesday: We resumed the framing, and we are now almost done with it.
Wednesday: We started work on the staircase, we decided that it would have a total of 17 steps at 7 3/8" high and 10 1/2" depth. we got the stair stringers marked out, and one finished.
Friday: We finished work on the staircase by cutting and installing the plywood on it.