One half of the roof sheathing is on and "dryed in" with ice and water shield and underlayment.
Saga crew plans on finishing the second half of the roof "dry in" on Monday and Tuesday of next week.








Trusses up and roof sheathing begins.








Thursday, December 9, 2010

Trusses go up and we get closer to having a roof on.






1st Truss (front gable) goes up today. The next trusses should go faster now that the first truss is plumb and in place. Plan on getting trusses done on Thursday and Friday this week.


















Wednesday, December 8, 2010

We have installed the two beams and posts to support the carport roof. The weather has been cooperating with no precipitation for two days now. Next we install roof trusses.

























Thursday, December 2, 2010

Walls are level, plumb and square and we are now very close to putting up the roof trusses. Hopefully at the beginning of next week.



Tuesday, November 30, 2010

We are back at the project after our Thanksgiving Break. Conditions have deteriorated for construction. It is our hope to true up exterior 2nd floor walls and install roof trusses soon. The snow is definately slowing progress. Students are dressing for the weather and have a great attitude.


























Thursday, November 18, 2010

Today the Basic Construction class finished and raised another 2nd floor wall.























Wednesday, November 17, 2010

We have been framing the 2nd floor walls in beautiful clear and cold weather.







































































Tuesday, November 9, 2010

11-9-10 Today was a beautiful day and we installed 2nd floor joists.