Week 2/8 - 2/12
Monday: Day off
Tuesday: finished the last of the Tyvek wrap around the house.
Wednesday: Dug a hole for the subterranean pipe-network in the garage.
Friday: Today we unloaded a delivery of shingles, windows, and pink-board. We also had several new people start working with us from SAGA
Week 2/1 - 2/5
Monday: Today we had a framing inspector come and inspect the house so far, we passed the inspection and can now move on to wrapping the house.
Tuesday: Started to wrap t he house in Tyvek which will help keep out moisture.
Wednesday: Continued to add Tyvek to the house.
Friday: Today we kept adding the Tyvek, but it became more complicated due to the areas needing to be covered being fairly high off the ground.
No comments:
Post a Comment