Saturday, February 6, 2010

weeks 2/1 - 2/5 and 2/8 - 2/12

Week 2/8 - 2/12

Monday: Day off

Tuesday: finished the last of the Tyvek wrap around the house.

Wednesday: Dug a hole for the subterranean pipe-network in the garage.

Friday: Today we unloaded a delivery of shingles, windows, and pink-board. We also had several new people start working with us from SAGA



Week 2/1 - 2/5

Monday: Today we had a framing inspector come and inspect the house so far, we passed the inspection and can now move on to wrapping the house.

Tuesday: Started to wrap t he house in Tyvek which will help keep out moisture.

Wednesday: Continued to add Tyvek to the house.

Friday: Today we kept adding the Tyvek, but it became more complicated due to the areas needing to be covered being fairly high off the ground.