Week 5/24 - 5/28

Monday: We finished up the ventilation job today by painting a sealant over any seams and joints we found in order to keep air from escaping.

Tuesday: We all did odd jobs today in order to get the house ready for inspection and drywall.

Wednesday: Today we started adding in the interior insulation. This task was made miserable by the fact that we all needed to wear long sleeve shirts and pants, a dust mask, and deal with insulation all on a very warm day. This was also the last day of class for our seniors Chris Budbill and Dan Turner.

Friday: We added in some more insulation and cleaned up the job site.