Thursday, April 21, 2011

This week, we caulked and sided the north eve side of the home and start placing starter shingles on the main roof.  Along with siding, we did some pick-up framing installing the upstairs bathroom sliding door, dug most of the trench for the electrical line, installed the exhaust through the carport for the HRV system, and finished installing all the exterior doors.  Next week, its on to the South side of the home then finally onto the main roof pending sunny weather. 

No comments:

Post a Comment