Week 4/12 - 4/16. This week we managed to complete the majority of the roofing, and continued with the pick-up framing.
Monday: We continued the pick-up framing from last week, and finally got started on adding the shingles to the roof.
Tuesday: Today we had two new guys from Angoon that were here as part of a career exploration program. They helped us continue our work from Monday.
Wednesday: We finished the first half of the roof and began working on the next side.
Friday: We almost finished adding the shingles, all that's left to do is add the roof cap.