Tuesday: Following a last minute deck design change, the deck railing was completed with a new twist. We used copper piping as vertical supports in place of traditional 2x2 spindles. This not only increases visibility through the deck railing, but adds another unique design feature that is durable and long-lasting.
Wednesday: With the deck railing completed, we focused our attention to interior finish work. The first order of business is a thorough cleaning in preparation for the delivery of cabinets. This cleaning will also help prep for the installation of flooring the rest of the week.
Thursday: Cabinets were delivered in the morning. For most of the day work continued on installing the flooring. With snap-together laminate, once the first row is down work moves pretty quickly!
Friday: A majority of the flooring was installed and some cabinets were set into place. We also laid tile in both bathrooms and the kitchen.
No comments:
Post a Comment